Upstream

Upstream

Upstream

 

← Back to Lost Hills Field Expansion

Overview

Nations Petroleum is constructing a new heavy oil facility and expanding their thermal production. This project encompasses two separate producing zones and will increase in supply from 300 BOPD to approx. 45,000 BOPD. The project scope includes high and low pressure steam injection systems; wet LACT measurements to determine royalties; centralized treatment facilities; produced water filtration and softening processes; and steam distribution systems. The project required acquisition of 30 easements for facilities and pipeline corridors. To allow early steam production, the team implemented a two-stage delivery schedule, which utilizes permanent and temporary rental equipment.

Back to Service

Information

Location
Lost Hills, California

Market
Upstream

MENU